MRP demands for Sub-Assemblies not Listed on SO?

Q.  If a BOM with sub-assemblies exist, will MRP requirements be created for the Sub-assemblies when only the top level is entered into the Sales order?

 

A.  MRP will explode the requirements down 99 levels for all components and subassemblies reporting to a top level assembly required by a sales order.  For further information see the Bill of Materials Management procedures and the Materials Requirements Planning Management producedures..