A/P Summary-Over 60 tab field Definitions
|
In the column below, the name of the supplier.The user may sort alpha by depressing the button.
|
|
In the column below, the net due to the user for that supplier.The user may sort on highest to lowest by depressing the button.
|
61 - 90 |
The amount due to the user which is 61 to 90 days past the due date. The Ranges for the Aging screens must be setup within the Purch A/P Setup module
|
91 – 120 |
The amount due to the user which is 91 to 120 days past the due date. The Ranges for the Aging screens must be setup within the Purch A/P Setup module
|
Over 120 |
The amount due to the user which is over 120 days past the due date. The Ranges for the Aging screens must be setup within the Purch A/P Setup module
|
Totals |
The totals line will display the totals for each column, Balance, 61-90, 91-120, Over 120.
|
Past Due All |
The grand net total for all of the suppliers for amounts past the scheduled due date.
|
Highlight the Supplier of interest.To view the detail, select the appropriate tab – A/P Detail Current – 60 or A/P Detail – Over 60.The detail for that Supplier will display.
|