Schedule a Work Order
Begin by Finding a Work Order, by depressing the Find button, or open the UnScheduled screen.



Highlight an Unscheduled Work order, then go to the Work Order screen: 
 
 
To schedule, click on the Edit Button and type in your password. 
 
 

Todays date will default in the Scheduled Start Date and the Work Order Due date will default in the Scheduled Complete date.  User may change these dates if necessary.

Note:  If the system cannot schedule by the given Schedule Complete Date (based on the process time required) it will schedule by the earliest possible date. Note:  The Schedule Complete Date may not match the Completion Date or Last Date Out.  System will not allow the Schedule Complete Date to be earlier that the Scheduled Start Date. User will receive the following warning if they have have entered a Schedule Complete Date earlier that the Schedule Start Date and will be required to change the Schedule Complete Date, before proceeding. 





Depress the Schedule button and the system will schedule the work order using the data entered in the
Work Order Traveler Setup module.



User can setup the Priority for each individual work centers within the Work Order screen, create or view the Work Order and/or Work Center Notes, and view any shortages for this Work order as displayed in the following screen..


Depress the Exit button.  Depress the Save button to save the schedule. Depress the Abandon Changes button to abandon the schedule.
User will then receive a prompt upon saving asking if user would like to schedule another job, and if yes it will open the "Find" window and continue to the "Edit" mode without asking for the password again.