1. Fields and Definitions for Production Capacity Setup
1.1. Capacity Summary Screen
 
 
 
Work Center List of all the Work Centers setup in the Production Work Center and Activities module.
Sh No The shift number setup in the Work Shift Setup module.
Description The description of the shift setup in the Work Shift Setup module.
From The beginning of the shift.
To The end of the shift.
Total Hrs Total time actually working, does NOT including breaks and lunches.
 
Selected Work Center Daily Capacity
 
Hours The total hours required for the work center highlighted, based on the shift hours and the resource..
Volume The total volume for the work center highlighted based on the shift hours, resource, and standard rate.

 

 

 

 

1.2. Resource Setup Screen
 
 
 
Work Center A List of all the Work Centers setup in the Production Work Center and Activities module
Activity A List of Activities for the Work Centers setup in the Production Work Center and Activities module.
Cap

Notice there are three activities listed, but only 2 of them (“Activity-1” and “Activity-5”) will be calculated in the capacity because the “Cap” box has been checked in the Production Work Centers & Activities module.

Sh No Shift Number assigned to the Work Shift in Work Shift Setup
Description The description of the shift setup in the Work Shift Setup module.
From The beginning of the shift.
To The end of the shift.
Total Hrs The total hours for the shift. 
Resource Assignment
This could be the number of people working during one given shift on a particular day or number of machines, or both, it is up to the user to decide.  The capacity for the given work center will be calculated by multiplying working hours for all the shifts set for any given WC on any give day times resources. Example:  If WC1 has one 8 hour shift set on Monday with number 8 (8 people) as a resource during this shift, the capacity for WC1 for that day would be 8*8=64 hours. 

NOTE: Each time a user enters the Capacity Setup module, the program checks the current date, and updates the month in the "Resource Assigment" grid to show the 12 months from current month.  For Example:  If the last time a user entered the module was March, so the 12 months are March/2008 to February/2009 (as displayed below).  If user re-enters this module in June, the program will change the 12 months to June/2008 to May/2009 and also assign "1" to the 3 new new added months (March, April, and May/2009). 
1.3. Activity Capacity View Screen
 
 
Work Center A List of all the Work Centers setup in the Production Work Center and Activities module.
Activity A List of Activities for the Work Centers setup in the Production Work Center and Activities module.
Cap Notice there are three activities listed, but only 2 of them (“Activity-1” and “Activity-5”) will be calculated in the capacity because the “Cap” box has been checked in the Production Work Centers & Activities module.
Sh No Shift Number assigned to the Work Shift in Work Shift Setup module.
Description The description of the shift setup in the Work Shift Setup module.
From The beginning of the shift.
To The end of the shift.
Total Hrs The total hours for the shift.
 
Selected Activity Daily Capacity
 
Hours The total hours required for the work center highlighted, based on the shift hours and the resource.
Volume The total volume for the work center highlighted based on the shift hours, resource, and standard rate.