The following setup is required before the user will be able to use the Production Capacity Schedule.
After activation, "Production Capacity Setup" access for each user must be setup in the ManEx System Security module. Users with “Supervisor Rights” will automatically have access.
Work Shifts must be setup in the Work Shift setup module. The more work hours you have the higher your capacity.
Within the Activity screen, the user checks the Cap Totaling box and enters the applicable Activity Costing information.
The Work Center Activity Setup and Run Times must be entered in the Work Order Traveler Setup module for any applicable product.
Check the status of the Work Order of interest – it can not be on Administrative Hold (for example), to complete the scheduling.
|