After activation, "Material Requirements Planning" (MRP) access for each user must be setup in the ManEx System Security module. Users with “Supervisor Rights” will automatically have access.
Material Requirements Planning Hot List Field Definition:
Days Late |
If the action date is earlier than the current date, the number of days late for the action is shown.
|
Required Date |
The date when the component part number highlighted is(was) required to be released to the assembly floor. |
Action |
The Material Requirements Planning action required. |
Part Number |
The Part Number for the item highlighted. |
Class |
The classification of the highlighted part number.
|
Type |
The Part Type assigned to the item.
|
Quantity |
The quantity of parts involved in the Material Requirements Planning action.
|
Buyer |
The valid buyer of the item highlighted |
|