What do some of these WO actions mean?

-Work Order Past Due: WO is not firm planned and the WO qty is still required to fulfill the SO demand. however WO is not complete yet so behind schedule on the WO due date.

 

 

-Cancel Work Order:WO is not kitted and not firm planned and qty's are not required to fulfill any demand.

 

 

-No WO Action: WO due date is still not past due to fulfill the demand requirement. Qty of WO matches demand requirement, Kit is not started and not firm planned either. Therefore no actions required by the user. 