How is the SO Lead Time Calculated?

Within the Sales Order module there is a button called “SO Lead Time.”This button will display the Longest Lead Time based on the following:

Component Purchase Lead Time          12 weeks (60 days)

Product Kitting Lead Time                     2 days

Product Production Lead Time               7 days

Total Sales Order Lead Time                 69 days



This should match the Lead Times from the Bill of Material Lead Time report.
 
 
Note:   The SO lead-time does NOT calculate the purchase lead-times of buy parts associated to sub assemblies. It will consider the kitting and production lead-times of the make part itself along with any buy components on the top level assembly in calculating the longest lead-time.  The system assumes that the sub-assembly is complete at the time your kitting it for the top assembly.
Article ID: 150