Within the Sales Order module there is a button called “SO Lead Time.”This button will display the Longest Lead Time based on the following:
Component Purchase Lead Time 12 weeks (60 days)
Product Kitting Lead Time 2 days
Product Production Lead Time 7 days
Total Sales Order Lead Time 69 days
This should match the Lead Times from the Bill of Material Lead Time report.
Note: The SO lead-time does NOT calculate the purchase lead-times of buy parts associated to sub assemblies. It will consider the kitting and production lead-times of the make part itself along with any buy components on the top level assembly in calculating the longest lead-time. The system assumes that the sub-assembly is complete at the time your kitting it for the top assembly.
|